Realizations
You are here :

Realizations

CHERKASSY BIOFUEL

 
MUNICIPAL COMPANY HEATING NETWORKS “CHERKASSYTEPLOKOMUNENERGO
 

 

 
Name of the customer
Address of the customer 62,O.Dashkovycha,Cherkasy, 18000, Ukraine
Nature of the works MUNICIPAL COMPANY HEATING NETWORKS “CHERKASSYTEPLOKOMUNENERGO
Address of the Construction site (Work) Design and Construction of the first Fully Automatic District Bio fuel Boiler Houses in Ukraine
Architect / Project manager  
Address of
the Project manager
 
Value of the total contract 717 620, 58  €
Duration of the works 8 months
Period of the works
Août 2010.
April 2011.
Description
of the realized works
 
Engineering, Procurement, Construction and Commissioning of a Fully Automatic Biofuel Boiler Plant
 
  • Boiler Room : 6 800 kW COMPTE-R / KOMKONT
  • Smoke Filtration system and Smoke Stack
  • Bio fuel Storage 100 m3
  • Bio fuel transporters to the boiler house
  • Ash and Dust removal system
  • Connection to district network through heat exchanger
MCHN “Cherkassyteplokomunenergo” Ltd.
 
[ See all realizations ]
 
The Group's
subsidiaries
Use the arrows to scroll
Cunin Fluids
Cunin Roofing
Cunin Maintenance
La Robinetterie (The Plumbing fitting)
Cunin Exportation
Cunin Russia
Cunin China
Enertex
Cunin Algeria
Brocard SARL
Cunin SARL
Cunin Industry
Imaginé par NEFTIS - CMS : Flexit©